Kettering premix site
Smith’s Concrete and Heidelberg Materials instructed the works to take place at there Kettering premix site.
- Decommission and dismantle the silos, arrange and plan the transportation of silos to there new homes.
- A full refurbishment was completed on the silo that was installed at Smiths Concrete Stratford Upon Avon site.
- A New Wham screw conveyor was installed to the silo.
- A Hycontrol silo protection system was installed along with a new Wham silo filtration unit.
- All integrations with the electrical systems and pneumatic systems was completed by STOCK ENGINEERING SERVICES.





Contact us